This research
studies resource constrained project scheduling problem in a part of a refinery
construction project in real world. In real world, most of the activities are
new and we have problems such as activity duration uncertainty. This problem
causes a change in a project makespan. The RCPSP is NP-hard. Hence, we proposed
an optimization method based on simulated annealing to solve the RCPS Problem.
In this paper, Fuzzy sets theory is used to represent this activity duration
uncertainty. Used schedule generation scheme, in the proposed simulated
annealing algorithm, is a fuzzy parallel scheduling generation method. Proposed
algorithm generates the minimum project makespan while considers renewable
resource-constrained and activity precedence and also has ability to perform
with fuzzy numbers for presenting project details such as start and final time
of activities and project whole time with fuzzy numbers. Finally, the results
of the algorithm will be evaluated and it will be represented that the proposed
algorithm is very efficient and can be used by managers and scheduling
programmers in real projects.